Project facts
| Status | Finished |
|---|---|
| Location | Lexton, VIC |
| Design | 2 bedroom kit home |
| Build team | Paul and Heather, owner builders |
| Foundations | ALLFOOT concrete-free steel footings by All Footings Solutions |
| Subfloor | Galvanised light gauge steel bearers and joists, footings to inspected subfloor in three days |
| Frame | Light gauge steel wall frames and roof trusses |
| Finish | Grey cladding, black framed windows and doors, elevated deck |

Paul and Heather owner-built their 2 bedroom kit home at Lexton. Instead of digging and pouring concrete pads, the home sits on ALLFOOT concrete-free steel footings by All Footings Solutions. Each footing is driven in and adjusted to height, ready for the steel subfloor.

Before anything was made, every stud, plate, brace and truss was modelled in 3D. These renders come straight from that frame model.

From above you can see how every truss lands on the wall frames below.

The footings go in row by row to match the subfloor layout. With no concrete to cure, the subfloor can start the next morning.

By the end of the first day every footing is in and set out across the block.

Day two starts with the subfloor posts and bracing fixed to the footings.

Everything is levelled with survey gear as it goes, so the subfloor ends up dead level across the slope of the block.

The light gauge steel bearers go on top of the posts, setting out the full footprint of the home.

By the end of day two the bearers are complete across the whole footprint.

Day three, and the light gauge steel floor joists go in across the bearers.

The joists are pre-cut and punched in the factory, so they fix straight on with no cutting on site.

Subfloor done and ready for inspection by the building surveyor. Everything is galvanised steel, so there is nothing to rot or attract termites.

From below you can see how the joists and bearers lock together into one rigid platform.

From bare ground to a finished, inspected steel subfloor in three days.

Next the wall frames and roof trusses go up on the subfloor, and the shape of the home appears.

With the trusses up, the frame is complete and ready for roof sheeting.

From the side the full frame sits up on its steel subfloor, clear of the ground.

From directly above, the room layout of the home is easy to read.

The finished home sits up on its steel subfloor with grey cladding and black framed windows and doors.

An elevated deck runs off the living area, with large windows looking out over the property.

From the side the steel supports under the home and deck are visible.