Paul and Heather’s Lexton Kit Home — Lexton, VIC

Project facts

StatusFinished
LocationLexton, VIC
Design2 bedroom kit home
Build teamPaul and Heather, owner builders
FoundationsALLFOOT concrete-free steel footings by All Footings Solutions
SubfloorGalvanised light gauge steel bearers and joists, footings to inspected subfloor in three days
FrameLight gauge steel wall frames and roof trusses
FinishGrey cladding, black framed windows and doors, elevated deck

ALLFOOT concrete-free steel footing with base plate installed in the ground at Lexton, Victoria
Day one — an ALLFOOT concrete-free steel footing goes in.

Paul and Heather owner-built their 2 bedroom kit home at Lexton. Instead of digging and pouring concrete pads, the home sits on ALLFOOT concrete-free steel footings by All Footings Solutions. Each footing is driven in and adjusted to height, ready for the steel subfloor.

3D render of the steel frame model for the Lexton kit home in Victoria
The frame model from the BIM file.

Before anything was made, every stud, plate, brace and truss was modelled in 3D. These renders come straight from that frame model.

3D render of the Lexton kit home in Victoria steel frame model from above, showing the roof trusses on the wall frames
From above, with the roof trusses sitting on the wall frames.

From above you can see how every truss lands on the wall frames below.

Rows of steel footings going in across the grassy block on day one at Lexton, Victoria
Footings going in across the block.

The footings go in row by row to match the subfloor layout. With no concrete to cure, the subfloor can start the next morning.

Steel footing posts set out across the block at the end of day one at Lexton, Victoria
All footings in by the end of day one.

By the end of the first day every footing is in and set out across the block.

Steel subfloor posts and bracing being fixed on the footings on day two at Lexton, Victoria
Day two — posts and bracing go on.

Day two starts with the subfloor posts and bracing fixed to the footings.

Steel footings and posts being levelled with survey equipment on site at Lexton, Victoria
Levelling everything with the survey gear.

Everything is levelled with survey gear as it goes, so the subfloor ends up dead level across the slope of the block.

Light gauge steel subfloor bearers fixed on posts across the block at Lexton, Victoria
Steel subfloor bearers on the posts.

The light gauge steel bearers go on top of the posts, setting out the full footprint of the home.

The steel subfloor bearers complete across the footprint at Lexton, Victoria
Bearers done by the end of day two.

By the end of day two the bearers are complete across the whole footprint.

Light gauge steel floor joists going in across the subfloor bearers at Lexton, Victoria
Day three — the joists go in.

Day three, and the light gauge steel floor joists go in across the bearers.

Steel floor joists installed along the length of the subfloor at Lexton, Victoria
Joists running the length of the subfloor.

The joists are pre-cut and punched in the factory, so they fix straight on with no cutting on site.

The completed galvanised light gauge steel subfloor ready for inspection at Lexton, Victoria
Subfloor done — inspector on his way.

Subfloor done and ready for inspection by the building surveyor. Everything is galvanised steel, so there is nothing to rot or attract termites.

Looking up at the galvanised steel joists of the completed subfloor at Lexton, Victoria
The completed subfloor from below.

From below you can see how the joists and bearers lock together into one rigid platform.

The finished steel subfloor at the end of day three at Lexton, Victoria
Footings to finished subfloor in three days.

From bare ground to a finished, inspected steel subfloor in three days.

Aerial view of the light gauge steel wall frames and roof trusses standing on the subfloor at Lexton, Victoria
Wall frames and roof trusses standing.

Next the wall frames and roof trusses go up on the subfloor, and the shape of the home appears.

Aerial view of the steel roof trusses erected over the wall frames at Lexton, Victoria
Roof trusses up over the walls.

With the trusses up, the frame is complete and ready for roof sheeting.

Aerial side view of the completed light gauge steel frame on its subfloor at Lexton, Victoria
The completed frame from the side.

From the side the full frame sits up on its steel subfloor, clear of the ground.

Top-down aerial view of the steel frame layout on the subfloor at Lexton, Victoria
Looking straight down on the frame.

From directly above, the room layout of the home is easy to read.

Finished Lexton kit home with grey cladding, gable roof and black framed windows on a raised steel subfloor at Lexton, Victoria
The finished home at Lexton.

The finished home sits up on its steel subfloor with grey cladding and black framed windows and doors.

The Lexton kit home with large windows and an elevated deck with black railings at Lexton, Victoria
Large windows and an elevated deck.

An elevated deck runs off the living area, with large windows looking out over the property.

Side view of the Lexton kit home showing the deck and steel supports at Lexton, Victoria
The deck and steel supports from the side.

From the side the steel supports under the home and deck are visible.